Workers: Proposal |
ANL plans to focus on three major areas (1 FTE, 230K + extra for Access Grid Training and Deployment)
- Design, Development and Hardening of Apple OS X version of the Access Grid (6 months) (addresses needs 7a - 7c)
- Venue VNC (5 months) (addresses needs of 7a - 7e)
- Private Audio in Room Environment (7g)
- (*) Access Grid Deployment and Training
Apple OS X Access Grid 2.0 (24 weeks)
- Porting of existing toolkit to OS X (4 weeks)
- Porting of existing media tools (4 weeks)
- Design of native media support (2 - 4 weeks)
- Development of native media support (4 - 6 weeks)
- Testing and bug fixes (6 weeks)
Venue VNC (Shared Applications from Access Grid) (20 weeks)
- Packaging, Documenting, Securing Current Version (4 weeks)
- Integration and Packaging (2 weeks
- GSI enabling (2 weeks)
- Development of Personal Services (16 weeks)
- Scenario -> Requirements -> Design -> Development -> Deployment
- Multicast
Private Audio in Room Environment (4 weeks)
- Bluetooth Audio Solutions
- Mixer Integration
- Documentation
Access Grid Deployment and Training (?? Effort)
- Deployment and Training
- Access Grid User Manuals
- Access Grid Programmers Manuals
- Tutorials on use of Access Grid